Project Status
Phases | Date (if applicable) | Status |
---|---|---|
Community Kick Off Meeting | Jan. 13, 2024 | Completed |
Conceptual Plan Presentation | Jan. 30, 2024 | Completed |
Final Concept Presentation | Feb. 13, 2024 | Completed |
Final Concept Approved by Board of Directors | May 1, 2024 | Completed |
Permits | July 25, 2024 | Completed |
Demo (demo will be completed in phases) | July 19, 2024 | Completed |
Build/Construction | July 31 - Current | Completed |
Completion & Grand Opening! | Oct. 5, 2024 | Completed |