The Lokker Park playground was renovated based on community feedback, capital budget, and District Board of Directors approval.  

Project Status

PhasesDate (if applicable)Status
Community Kick Off MeetingJan. 13, 2024Completed
Conceptual Plan PresentationJan. 30, 2024Completed
Final Concept PresentationFeb. 13, 2024Completed
Final Concept Approved by Board of DirectorsMay 1, 2024Completed
Permits July 25, 2024Completed 
Demo (demo will be completed in phases) July 19, 2024 Completed
Build/ConstructionJuly 31 - CurrentCompleted
Completion & Grand Opening! Oct. 5, 2024Completed

 

Design 

Playground Design Approved by Board of Directors on May 1

 

 